Workflow for a Project Control Engineer to perform effectively in controlling schedule, cost, and performance 🔹 1. Kick-off & Scope Definition Define WBS, OBS and project deliverables. Set the level of detail (LoD) 1-3 days Establish baseline schedule and budget 🔹 2. Build Control Structure Develop the schedule with logic ties, resources, and coding system. Create cost accounts per WBS element. Save and approve the baseline in Primavera, MS Project, or SAP. 🔹 3. Data Integration Daily reports (progress, manpower) Timesheets, procurement data HSE and QA/QC updates 🔹 4. Progress Measurement Physical % complete Earned Value (EV) Quantity-based progress reporting frequency (daily site input, weekly review). Validate reported progress with evidence — photos, inspection reports 🔹 5. Schedule & Cost Update Actual Start/Finish dates Percent Complete Actual Cost Recalculate (reschedule) Avoid unnecessary changes to baseline logic. 🔹 6. Performance Analysis (EVM & Schedule) Calculate Earned Value (EV), Planned Value (PV), and Actual Cost (AC). key indices: SPI = EV / PV CPI = EV / AC 🔹 7. Forecasting Estimate final cost and completion: EAC = AC + (BAC - EV) / CPI ETC = EAC - AC Forecast completion date using revised schedule. Present recovery or mitigation plan 🔹 8. Change Control Record all scope or budget changes through a formal process (RFC / CCB). Update baseline only after approval. Maintain a change log showing impact on cost & time. 🔹 9. Risk & Issue Management Maintain a risk register with probability, impact, owner, and mitigation plan. Quantify schedule and cost impact of each risk. Review and update risk register regularly (weekly or monthly). 🔹 10. Reporting & Communication Daily: short update Weekly: detailed progress + EVM report (SPI, CPI, variance). Monthly: management report with forecast, cost summary, and executive insights. Visuals — S-curves, Gantt charts, and performance dashboards. 🔹 11. Project Close-out As-built schedule Final EAC & variance report Lessons learned Handover documentation Archive all baselines, progress reports, and cost records. 🔹 12. Continuous Improvement Conduct lessons-learned sessions after milestones. Update templates, methods, and automation tools for future projects. 🧩 Typical Deliverables Category Document / Output Planning WBS, baseline schedule, cost breakdown Control Weekly/Monthly progress report, EVM dashboard Risk register & mitigation log Change Change request & approval record Forecast EAC/ETC report, recovery plan Close-out As-built schedule, final report, lessons learned 📅 Routine Activities Daily Site progress capture, update key activities, issue log Weekly Schedule & cost update, EVM analysis, progress meeting Monthly Forecast review, management report, risk update ⚙️ Tools & Best Practices Primavera P6, MS Project, Excel, Power BI, SAP. 📊 Key Formulas SPI EV / PV CPI EV / AC EACAC + (BAC - EV)/CPI VAC BAC - EAC TCPI (BAC - EV)/(BAC - AC)
Work Breakdown Structure (WBS) Development
Explore top LinkedIn content from expert professionals.
-
-
I was sitting in a WIP meeting with a PM and Superintendent last week. They were reviewing cost to completes and the PM asked about a job. The Super said they were 80% done on a job. The problem was they had burned 95% of the hours. I asked how frequently this happened and they both just kind of looked at each other. They didnt need to answer I already knew. Then I asked: "How are you tracking percent complete against cost used?" Silence again. They did not have a system to track percent complete, and tracking costs vs budget tells you what you've spent. It does not tell you what you've built. When 95% of your hours are gone, are you 95% complete? Maybe. But without a work breakdown Structure(WBS) tied to installed quantities, you don't actually know. By the time you find out you're behind, you're usually too far in to recover the margin. A WBS converts total estimated hours into daily production rates. Devices per day. Linear feet of pipe per crew hour. Square footage of surface prep per shift. It gives the field a number to hit. It gives leadership an early warning mechanism, Not a feeling. A specific, trackable rate that tells everyone whether the job is on track before it's too late. These targets should come from estimating collaborating with the field on prior performance, but they should also be set on what good looks like. Purely setting targets based on historical performance and you're estimating to your own inefficiencies. Set the target based on what good looks like. That's how you stop finding out about problems when your your 80% complete.
-
Have you ever thought about tracking progress directly on the scope in Primavera P6 Cloud? In my recent projects, I've been focusing more on measuring progress against scope rather than just time or cost. When your WBS is aligned with the contract deliverables, you can monitor how much of the actual work is done—not just how long it's taken. Here’s how I track scope progress in Primavera P6 EPPM (Cloud version): 🔹 1. Align the WBS with contractual scope Each WBS level reflects a specific deliverable or component of work. 🔹 2. Enable WBS Summary Activities These automatically roll up progress from lower-level activities. 🔹 3. Set % Complete Type to ‘Physical’ This allows for manual, more accurate progress entry based on real deliverables. 🔹 4. Add WBS-level milestones Helps in monitoring progress checkpoints tied to specific scopes. 🔹 5. Update Physical % Complete periodically I typically base this on field reports, inspection logs, or earned value calculations. 🔹 6. Visualize scope progress Using the P6 dashboard or integrated visuals in Power BI gives stakeholders real-time clarity. 💡 Bonus tip: Scope % complete can also be automated using formulas or field data integration to reduce manual effort. #Primavera #P6 #Scheduling #Consulting #Scope Learn more https://lnkd.in/gMYUqyDf
Explore categories
- Hospitality & Tourism
- Productivity
- Finance
- Soft Skills & Emotional Intelligence
- Education
- Technology
- Leadership
- Ecommerce
- User Experience
- Recruitment & HR
- Customer Experience
- Real Estate
- Marketing
- Sales
- Retail & Merchandising
- Science
- Supply Chain Management
- Future Of Work
- Consulting
- Writing
- Economics
- Artificial Intelligence
- Employee Experience
- Healthcare
- Workplace Trends
- Fundraising
- Networking
- Corporate Social Responsibility
- Negotiation
- Communication
- Engineering
- Career
- Business Strategy
- Change Management
- Organizational Culture
- Design
- Innovation
- Event Planning
- Training & Development