I was involved in settling a contractor’s claim. No court. No arbitration. Fixed compensation. But one question stayed with me: Where in the contract does it actually say the contractor has the right to claim? I didn’t know. So I picked up a book. "Construction Claims & Disputes" - Dr. Nabil Shehadeh, published by the Dubai Society of Engineers. What I found changed how I read contracts. There are 25 clauses in FIDIC 1999 (Red Book) that a contractor can use to claim time, cost, or both. Most QS professionals know Clause 20.1 - Contractor's Claims. Almost nobody reads the other 24. Here's what I've understood so far, simplified: When the client causes the delay : → Cl. 1.9 - Late drawings or instructions. Time + cost entitlement. → Cl. 2.1 - Delayed site access. If the agreed date slips, entitlement arises. → Cl. 8.5 - Authority delays (permits/approvals). Time is owed. When site conditions aren’t what was expected : → Cl. 4.12 - Unforeseen ground conditions. Major claim cause in Earthwork. → Cl. 4.24 - Fossils / archaeological finds. Contractor can't be penalised. When work gets suspended : → Cl. 8.9 - Engineer suspends work. If it exceeds 84 days, cost can be claimed. → Cl. 16.1 - Non-payment beyond 42 days. Contractor has the right to suspend work. When scope changes : → Cl. 12.3 - Valuation of variations. If the nature changes, rates can change. → Cl. 13.3 - Variation procedure. If the process isn’t followed, disputes begin. When things go wrong on site : → Cl. 7.5 - Failed tests. Liability depends on specification responsibility. → Cl. 11.2 - Defects during DLP. If design-related, not contractor’s liability. → Cl. 11.8 - Search for defects. If nothing is found, the employer pays. → Cl. 17.4 - Employer’s risks (war, contamination). Contractor entitled to recovery cost. → Cl. 19.1 - Force majeure. Neither party at fault. Consequences are shared. When the project is closing : → Cl. 10.2 - Partial takeover. Disruption may lead to claims. → Cl. 10.3 - Interference with tests. If delayed, time entitlement arises. → Cl. 15.4 - Termination. Defines paid value for work done. When it becomes a dispute : → Cl. 20.1 - Notice within 28 days. Miss this & the claim may be barred. → Cl. 20.2 - Dispute Adjudication Board. Decision within 84 days. → Cl. 20.5 - 56-day amicable settlement before arbitration. → Cl. 20.7 - Ignoring DAB decision allows direct escalation to arbitration. I'm not an expert in FIDIC. I'm still learning. But reading these clauses made me realise something: Most claims don't fail because of bad facts. They fail because the contractor didn't know which clause protected him. The contract already has the answers. Most of us just never read far enough to find them. I've made a reference infographic displaying all 25 clauses So you don't have to flip through 80 pages to find the one you need. Save this. Bookmark it. Keep it open the next time a claim lands on your desk.
Understanding International Construction Contracts
Explore top LinkedIn content from expert professionals.
Summary
Understanding international construction contracts means recognizing that these agreements set the rules, responsibilities, and risk-sharing for complex, cross-border building projects. These contracts determine how costs, timelines, design changes, and disputes are handled between parties from different countries, making clarity and careful review essential for project success.
- Know your contract: Take time to understand which type of construction contract fits your project, since each model allocates risk and control in different ways.
- Clarify design responsibilities: Make sure the contract clearly defines who is responsible for design decisions and errors to avoid confusion and costly delays.
- Document and communicate: Always keep thorough records of changes, notices, and decisions, as clear communication and documentation are crucial for resolving any disputes.
-
-
⚙️EPC, EPIC, EPCC, EPCIC, EPCM — understanding the differences matters In large-scale industrial, oil & gas, marine, and infrastructure projects, the type of contract you choose defines the execution strategy, risk ownership, cost certainty, and level of client involvement. Here’s a breakdown in plain language: 🔹 EPC – Engineering, Procurement, Construction A traditional turnkey approach. The contractor designs the facility, procures all materials and equipment, constructs the works, performs pre-commissioning, and hands over a plant ready for commissioning. ✅ Low client involvement during execution ⚠️ Contractor carries most of the cost, schedule, and quality risk 🔹 EPIC – Engineering, Procurement, Installation, Commissioning A variation of EPC, common in offshore and marine projects. Instead of “construction,” the focus is on installation — offshore platforms, subsea pipelines, floating structures. Marine transport, heavy lifts, and weather risks are major factors. ✅ Ideal for offshore projects where installation is the main execution activity ⚠️ Higher technical and environmental risk 🔹 EPCC – Engineering, Procurement, Construction, Commissioning EPC with commissioning explicitly included in the contract. The contractor not only builds but also starts up and proves the facility meets all performance guarantees before handover. ✅ Client receives a fully operational facility ⚠️ Contractor bears performance risks and penalties for shortfalls 🔹 EPCIC – Engineering, Procurement, Construction, Installation, Commissioning An integrated model combining onshore and offshore execution. The contractor handles engineering, procurement, construction of onshore facilities, offshore fabrication, installation, and final commissioning. ✅ Single point of responsibility for field-to-plant delivery ⚠️ Highest complexity and combined onshore-offshore risk 🔹 EPCM – Engineering, Procurement, Construction Management Not a turnkey contract — here the contractor manages the design, procurement, and construction on behalf of the client. The client holds contracts with suppliers and builders, keeping control but also retaining most risks. ✅ High flexibility and owner control over vendors ⚠️ Requires an experienced and resourceful client team 💡 In short: EPC / EPCC / EPCIC = Turnkey delivery, low client control, high contractor risk. EPIC = Offshore-focused turnkey with installation emphasis. EPCM = Management role, high client control, high client risk. Choosing the right model depends on project complexity, location, risk appetite, contracting strategy, and desired level of owner control. ✨ Found this helpful? 🔔 Follow me Krishna Nand Ojha, and my mentor Govind Tiwari,PhD for insights on Quality Management, Continuous Improvement, and Strategic Leadership Let’s grow and lead the quality revolution together! 🌟 #EPC #EPCM #EPIC #EPCC #EPCIC
-
#Design #Risk in #FIDIC #Contracts Deep Dive into #Design #Risk 📢 FIDIC #contracts are widely used for #international #construction projects, but #design risk can be a tricky issue to navigate. Let's delve deeper: What is #Design Risk? Design risk refers to the possibility that the project's design might be incomplete, inaccurate, or even flawed when the #FIDIC contract is signed. This can lead to unforeseen 🕶 problems during construction, causing ⏰ delays, extra 💲 costs, and potential 🤼♂️ disputes. Who Bears the #Risk? FIDIC contracts offer flexibility in allocating design risk. Here are the common scenarios: Employer Takes the Risk (Typical Scenario): In most #FIDIC forms (like the Red Book), the employer shoulders design risk. This means they're responsible for any additional costs arising from design errors or omissions. This makes sense if the employer provides the design or has significant control over it. Contractor Takes the Risk (Less Common): This scenario is more likely with the Silver Book, where the contractor designs and builds. The contractor bears the risk for any design flaws leading to extra costs. This usually happens when the employer provides a high-level concept design but leaves the details to the contractor. Shared Risk: The contract can be drafted to share design risk between employer and contractor. This might involve a threshold for additional costs due to design errors. Costs below the threshold might fall on the contractor, while the employer absorbs anything exceeding it. How to Manage #Design Risk? Clear Contract Clauses: The contract should explicitly address design risk allocation. This includes defining the level of detail expected in the Employer's Requirements and the contractor's design responsibilities. Detailed Design Review: Before signing the contract, both parties should conduct a thorough review of the design documents. This helps identify potential issues and allows for adjustments before construction begins. Communication and Documentation: Clear and consistent communication is crucial. Documenting all design discussions, decisions, and approvals throughout the project creates a clear record in case of disputes arising from design flaws. Contingency Planning: It's wise to consider potential design risks and develop contingency plans to address them. This could involve including buffer time in the schedule and budget to accommodate unforeseen design changes. By proactively managing design risk, both employers and contractors can minimize the possibility of costly delays and disputes during construction. Cost Overruns: If the design needs significant changes during construction, additional costs can arise for materials, labor, and time delays. Delays: Fixing design flaws during construction can significantly slow down the project schedule. Disputes: Disagreements between the employer and contractor about who is responsible for the additional costs and delays can arise.
-
2- 𝐃𝐞𝐜𝐨𝐝𝐢𝐧𝐠 𝐅𝐈𝐃𝐈𝐂: 𝐌𝐚𝐤𝐢𝐧𝐠 𝐒𝐞𝐧𝐬𝐞 𝐨𝐟 𝐭𝐡𝐞 𝐅𝐢𝐧𝐞 𝐏𝐫𝐢𝐧𝐭 (𝐒𝐨 𝐘𝐨𝐮 𝐃𝐨𝐧'𝐭 𝐆𝐞𝐭 𝐁𝐮𝐫𝐧𝐞𝐝) Based on the many 𝐃𝐌 𝐦𝐞𝐬𝐬𝐚𝐠𝐞𝐬 and communications that continued throughout the past week from many colleagues who follow and are interested in contracts, especially the FIDIC, to detail the authors’ point of view regarding, ever stared at a FIDIC contract and felt like you're reading ancient hieroglyphs? You're not alone The"𝐅𝐈𝐃𝐈𝐂 - 𝐋𝐚𝐰 𝐚𝐧𝐝 𝐏𝐫𝐚𝐜𝐭𝐢𝐜𝐞"book is a deep dive into these contracts, and one of the most crucial things it tackles is how we actually understand and use them 1. 𝐈𝐭'𝐬 𝐍𝐨𝐭 𝐉𝐮𝐬𝐭 𝐀𝐛𝐨𝐮𝐭 𝐑𝐞𝐚𝐝𝐢𝐧𝐠 𝐭𝐡𝐞 𝐖𝐨𝐫𝐝𝐬, 𝐈𝐭'𝐬 𝐀𝐛𝐨𝐮𝐭 𝐔𝐧𝐝𝐞𝐫𝐬𝐭𝐚𝐧𝐝𝐢𝐧𝐠 𝐭𝐡𝐞 𝐈𝐧𝐭𝐞𝐧𝐭: We need to understand the reasoning behind the clauses. Think of it like designing a bridge: you don't just follow the specs blindly; you need to understand the structural principles The book explains how courts and arbitrators interpret these contracts, focusing on what the parties intended when they wrote them 2. "𝐅𝐚𝐢𝐫 𝐃𝐞𝐭𝐞𝐫𝐦𝐢𝐧𝐚𝐭𝐢𝐨𝐧" 𝐢𝐬 𝐘𝐨𝐮𝐫 𝐅𝐫𝐢𝐞𝐧𝐝 (𝐚𝐧𝐝 𝐘𝐨𝐮𝐫 𝐑𝐞𝐬𝐩𝐨𝐧𝐬𝐢𝐛𝐢𝐥𝐢𝐭𝐲): A recurring theme is the concept of "fair determination," especially when it comes to the Engineer's role The book stresses that decisions made under FIDIC (variations, valuations, etc.) must be reasonable and impartial. The book details how to properly document the rational behind your decisions, which will be essential should any dispute arise. 3. 𝐍𝐨𝐭𝐢𝐜𝐞𝐬, 𝐍𝐨𝐭𝐢𝐜𝐞𝐬, 𝐍𝐨𝐭𝐢𝐜𝐞𝐬! (𝐃𝐨𝐧'𝐭 𝐈𝐠𝐧𝐨𝐫𝐞 𝐓𝐡𝐞𝐦): FIDIC contracts are very strict about notices Miss a deadline, and you could lose your right to claim Essentially, treat notices like critical communication in any other engineering project The book gives practical examples of how to properly draft and serve notices, which is invaluable 4. 𝐃𝐞𝐬𝐢𝐠𝐧-𝐁𝐮𝐢𝐥𝐝 𝐃𝐢𝐟𝐟𝐞𝐫𝐞𝐧𝐜𝐞𝐬: For those working on Yellow or Silver Book projects, the book highlights the crucial differences in how contracts are interpreted. The "Employer's Requirements" and the "Contractor's Documents" become central to the contract. The Book explain how these documents are interpreted and how they interact with each other 5. 𝐏𝐫𝐚𝐜𝐭𝐢𝐜𝐚𝐥 𝐀𝐩𝐩𝐥𝐢𝐜𝐚𝐭𝐢𝐨𝐧: Understanding how a court or arbitrator would interpret the contract, engineers will be able to make better informed decisions In essence, "FIDIC - Law and Practice" encourages engineers to: Think critically about the contract, not just memorize clauses. Document everything. 𝐈𝐟 𝐲𝐨𝐮 𝐚𝐩𝐩𝐥𝐲𝐢𝐧𝐠 𝐭𝐡𝐞𝐬𝐞 𝐩𝐫𝐢𝐧𝐜𝐢𝐩𝐥𝐞𝐬, 𝐲𝐨𝐮'𝐥𝐥 𝐛𝐞 𝐛𝐞𝐭𝐭𝐞𝐫 𝐞𝐪𝐮𝐢𝐩𝐩𝐞𝐝 𝐭𝐨 𝐧𝐚𝐯𝐢𝐠𝐚𝐭𝐞 𝐭𝐡𝐞 𝐜𝐨𝐦𝐩𝐥𝐞𝐱𝐢𝐭𝐢𝐞𝐬 𝐨𝐟 𝐅𝐈𝐃𝐈𝐂 𝐜𝐨𝐧𝐭𝐫𝐚𝐜𝐭𝐬 𝐚𝐧𝐝 𝐚𝐯𝐨𝐢𝐝 𝐜𝐨𝐬𝐭𝐥𝐲 𝐝𝐢𝐬𝐩𝐮𝐭𝐞𝐬 #Claims #contract #project #corrective_action #GIGA_Projects #CDBA #cash_flow_gap #Value_Stream_Management #PMO #CDP #PPP
-
🌍 Understanding the 9 Types of Construction Contracts: A Guide Every Project Professional Should Know In the construction and infrastructure world—especially water, wastewater, and large industrial projects—the type of contract you choose will determine cost control, risk distribution, project speed, and even team behavior. 👉 Success is not only about executing the project… It’s also about choosing the right contract model from the start. Below is a clear breakdown of the 9 major construction contract types 1️⃣ Lump Sum (Fixed Price) A single price for delivering the whole project. ✔ High cost certainty ✔ Best for well-defined scope ⚠ Variations can become expensive Used in: Buildings, EPC works with clear designs 2️⃣ Unit Rate (Re-measurement Contract) Contractor is paid based on actual quantities executed. ✔ Flexible for uncertain quantities ✔ Fair measurement-based payment ⚠ Final cost can vary Used in: Pipelines, roads, utility networks 3️⃣ Cost Reimbursable (Cost-Plus) Client pays actual cost + contractor’s fee. ✔ Great when speed is needed ✔ Ideal for evolving scope ⚠ Client carries most of the risk Used in: Fast-track or specialist works 4️⃣ Time & Materials (T&M) Payment based on actual time, manpower, and materials. ✔ Flexible and fast to mobilize ⚠ Requires strict supervision Used in: Maintenance, corrective works, small tasks 5️⃣ EPC / Design-Build Contractor handles Engineering, Procurement & Construction. ✔ Single point of responsibility ✔ Faster delivery & optimized design ⚠ Owner has limited design control Used in: Water plants, desalination, power plants, industrial facilities 6️⃣ Guaranteed Maximum Price (GMP) A cap on the total cost, even under a cost-plus model. ✔ Protection for client ✔ Incentive for contractor to reduce costs ⚠ Contractors add contingency to the GMP Used in: Mid-size projects with evolving scope 7️⃣ BOT / PPP / Concession Contracts Private sector finances, builds, operates, then transfers. ✔ Zero upfront cost for client ✔ Ensures quality through long-term operation ⚠ Complex structure & long negotiation Used in: Desalination plants, wastewater treatment, large infrastructure 8️⃣ Turnkey Contract Contractor delivers a fully operational facility “ready to run.” ✔ Maximum convenience for the client ✔ High certainty ⚠ Higher cost due to higher contractor risk Used in: Industrial plants, packaged facility delivery 9️⃣ IPD – Integrated Project Delivery A collaborative model where client, designer, and contractor share risks & rewards. ✔ Reduces conflict and claims ✔ Encourages innovation ⚠ Requires very high trust and transparency Used in: High-collaboration or complex projects 🔍 Why This Matters Choosing the right contract type shapes everything: Cost certainty Risk allocation Procurement strategy Dispute potential Project speed Stakeholder responsibilities 💬 Final Thought A smart project manager selects the contract that balances risk, clarity, cost, and speed for that specific job.
-
FIDIC vs NEC – Two Standards, Two Mindsets When selecting the right contract standard, it’s not just about legal language—it’s about the philosophy behind project delivery. 🔹 FIDIC – Fédération Internationale des Ingénieurs-Conseils (International Federation of Consulting Engineers) A globally recognised suite of contracts focused on clarity, roles, and risk allocation. FIDIC is widely used for international infrastructure and construction projects, especially where multiple jurisdictions and large-scale capital investment are involved. 🔹 NEC – New Engineering Contract Developed in the UK, NEC contracts promote collaboration, flexibility, and early problem-solving. NEC is particularly effective for projects that need strong communication and adaptability—design-build, alliance contracting, and public-sector works included. 👉 FIDIC suits risk-sensitive environments where detailed provisions matter. 👉 NEC suits dynamic projects that benefit from shared risk and collaborative behaviours. Understanding these differences is essential to ensuring project success, contract alignment, and long-term value. Which one does your organisation prefer—and why? #CIPS #FIDIC #NEC #ContractManagement #InfrastructureProjects #ConstructionLaw #ProjectDelivery #ProcurementStrategy #CollaborativeContracts #RiskAllocation
-
Understanding Contract Types in Construction & Engineering Projects In the world of construction projects, selecting the right contract model is critical for balancing risk, cost, quality, and efficiency. Various contract types define the roles and responsibilities across Front-End Engineering Design (FEED), Engineering, Procurement, Construction, Commissioning, and Management, ensuring alignment with project objectives. 🔹 1️⃣ Engineering, Procurement & Construction (EPC) A turnkey model where the contractor takes full responsibility from engineering & design to procurement, construction, and commissioning. The owner gets a ready-to-operate facility, typically at a lump sum price, shifting most risks to the contractor. 🔹 2️⃣ Engineering, Procurement & Construction Management (EPCM) Unlike EPC, here the contractor manages the procurement & construction but does not perform the work directly. The owner retains greater control, and costs are often reimbursable, making it ideal for complex projects requiring flexibility. 🔹 3️⃣ Design-Build (DB) A single entity handles both design and construction, reducing coordination risks and improving speed. It is commonly used for fast-track projects where early contractor involvement optimizes design for constructability. 🔹 4️⃣ Design-Bid-Build (DBB) The traditional sequential model where design, bidding, and construction occur in phases. It provides cost transparency but may lead to longer timelines due to separate contracting stages. 🔹 5️⃣ Open Book Estimation (OBE) Contracts A collaborative approach where contractors provide full transparency on cost structures, allowing owners to review actual costs, markups, and contingencies. Often used in cost-plus or target price models to build trust and ensure cost efficiency. 🔹 6️⃣ Build-Operate-Transfer (BOT) Used in infrastructure projects, the contractor finances, builds, and operates the project for a set period before transferring it to the owner. This minimizes upfront investment risks for clients. 🔹 7️⃣ Lump Sum (Fixed Price) vs. Cost-Plus Contracts Lump Sum: Contractor assumes risk, best for well-defined scopes. Cost-Plus: Owner pays actual costs + agreed fee, allowing flexibility but requiring robust cost controls. Each contract type shapes project execution, risk allocation, and financial structures. Selecting the right model depends on factors such as project complexity, risk appetite, schedule constraints, and quality expectations. 💡 Which contract models have you found most effective in your projects? Let’s discuss in the comments! #Construction #Contracts #EPC #EPCM #ProjectManagement #Quality #Engineering #Procurement #ConstructionLeadership #RiskManagement #OpenBookEstimation
-
50 Construction Contract Terminologies Ever felt lost in a construction contract conversation? I’ve been there too. Where terms fly across meeting rooms faster than decisions. So I decided to put together this wall-chart for beginners — not from textbooks, but from the real trenches of contracts and claims management. No jargon. Just plain, useful definitions. Whether you're a Site Engineer trying to understand your first Variation, or a Project Director cross-checking a Termination clause — this one’s for you. Here’s your vocabulary cheat sheet — Save it, share it, train with it. Contract Client Contractor Consultant/PMC Parties LOA (Letter of Acceptance) Commencement Date Time for Completion Taking Over Certificate Performance Security Advance Payment Variation EOT (Extension of Time) Prolongation Cost Clause 20 Notice Contemporary Records Dispute Claim Variation Order (VO) Cost Plus Profit Dispute Adjudication Board Arbitration Amicable Settlement Notice of Dissatisfaction Final and Binding Defects Notification Period Snag List As-Built Drawings Works Client’s Requirements Contractor’s Proposal Shop Drawings Site Commencement Instruction Interim Payment Certificate Force Majeure Sub-Clause Termination Default Indemnity Assignment Notice to Correct Suspension Liquidated Damages (LDs) Subcontractor Bill of Quantities (BOQ) Provisional Sum Retention Money Final Account Payment Schedule Tag your young engineers, interns, or even your own project team. We don’t just build projects. We build understanding too. Was this helpful ? ♻ Share this to EDUCATE your network and stay engaged with Ilamparithi BoologaSundaraVijayan Insights for more! ------------------------------------------------------------------------------------ 📚𝑩𝒐𝒐𝒌𝒔 𝒃𝒚 𝑨𝒖𝒕𝒉𝒐𝒓: 📕Construction Contracts Management for Beginners 📗Construction Contract Claims 📘100 Construction Contract letter Templates: From Contractor to Employer 📒100 FAQS in EPC/Construction Contracts 📓Role of Procurement in EPC 🔗https://lnkd.in/gH4gfkvk ------------------------------------------------------------------------------------- 🚀𝐆𝐞𝐭 𝐘𝐨𝐮𝐫𝐬𝐞𝐥𝐟 𝐄𝐧𝐫𝐢𝐜𝐡𝐞𝐝 𝐰𝐢𝐭𝐡 𝐭𝐡𝐞 𝐅𝐚𝐬𝐭-𝐌𝐨𝐯𝐢𝐧𝐠 𝐂𝐨𝐮𝐫𝐬𝐞𝐬!!! 🎓𝐂𝐨𝐧𝐬𝐭𝐫𝐮𝐜𝐭𝐢𝐨𝐧 𝐂𝐨𝐧𝐭𝐫𝐚𝐜𝐭 𝐂𝐨𝐮𝐫𝐬𝐞𝐬 📌 Advanced Diploma in Construction Contracts Management (8 hours) 📌 Advanced Diploma in Construction Claims Management (10 hours) 📌 Master Diploma in Construction Contracts & Claims Management (16 hours) 🔗 Register now and learn from the best! WhatsApp +91 75399 24659 | ✉ services@pragmaticpc.com ------------------------------------------------------------------------------------- 📢 Stay updated with our latest insights, updates, and opportunities! Join my 𝑾𝒉𝒂𝒕𝒔𝑨𝒑𝒑 𝑮𝒓𝒐𝒖𝒑 now to be part of our growing community. Click the link below to join: 🔗 https://lnkd.in/g3-fjAVS
Explore categories
- Hospitality & Tourism
- Productivity
- Finance
- Soft Skills & Emotional Intelligence
- Project Management
- Education
- Technology
- Leadership
- Ecommerce
- User Experience
- Recruitment & HR
- Customer Experience
- Real Estate
- Marketing
- Sales
- Retail & Merchandising
- Science
- Supply Chain Management
- Future Of Work
- Consulting
- Writing
- Economics
- Artificial Intelligence
- Employee Experience
- Healthcare
- Workplace Trends
- Fundraising
- Networking
- Corporate Social Responsibility
- Communication
- Engineering
- Career
- Business Strategy
- Change Management
- Organizational Culture
- Design
- Innovation
- Event Planning
- Training & Development