window analysis

window analysis


WINDOW ANALYSIS PROCEDURE IN PRIMAVERA P6

(Also known as “Contemporaneous Schedule Window Analysis” or “As-planned vs As-built Window Analysis”)

Window Analysis evaluates project delays by breaking the schedule into multiple time-windows and comparing progress period by period.


1️⃣ PREPARATION

1. Collect the required data

  • Baseline schedule (Approved baseline in P6)
  • Progress updates (monthly/weekly updates)
  • As-built information
  • Delay events list + dates/impacts
  • Any approved change orders

2. Set your baseline

  1. Go to Project → Assign Baselines
  2. Select:


2️⃣ DEFINE THE WINDOWS

A window is typically a period between two updates (e.g., Monthly windows).

Examples:

  • Window 1 → Start to Update #1
  • Window 2 → Update #1 to Update #2
  • … and so on until final update.


3️⃣ DUPLICATE THE SCHEDULE FOR ANALYSIS

For each window, you need a working copy.

  1. Go to Projects → Copy
  2. Paste as “Window 1 – Analysis”, “Window 2 – Analysis”, etc.
  3. Keep the original updates untouched for audit purposes.


4️⃣ PERFORM WINDOW 1 ANALYSIS

Step A: Open “Window 1” project

  • Load the as-planned schedule and the first as-built update.

Step B: Set the Data Date

  1. Go to Project → Dates
  2. Set Data Date = End of Window 1 (e.g., update date)

Step C: Apply actuals

Import or apply:

  • Actual start / finish
  • Remaining duration
  • % complete
  • Progress achieved up to Window 1

Step D: Run the Schedule

  1. Press F9 (Schedule)
  2. Ensure options:

Step E: Compare Baseline vs Updated Schedule

Go to Tools → Tracking → Gantt Chart and compare:

  • Total float changes
  • Critical path shifts
  • Activity delays
  • Variances (Start/Finish/Duration)

Step F: Identify delays in Window 1

Classify each delay:

  • Excusable vs Non-excusable
  • Compensable vs Non-compensable
  • Contractor vs Owner
  • Critical-path impacts

Document:

  • Delay cause
  • Impact days
  • Activities affected
  • Whether acceleration/mitigation happened


5️⃣ PERFORM WINDOW 2, 3, 4… ANALYSIS

Repeat the same process for each new schedule window:

For each Window:

  1. Copy the updated schedule
  2. Set Data Date to next update
  3. Apply actuals
  4. Schedule the project
  5. Review float & critical path changes
  6. Identify delays unique to each window
  7. Record cumulative impacts


6️⃣ BUILD THE WINDOW ANALYSIS REPORT

For each window, include:

A. Period description

  • Dates from → to
  • Activities worked
  • Major progress events

B. Baseline vs Period Variance

  • Start variances
  • Finish variances
  • Float consumption
  • Critical-path movement

C. Delay Events

For each delay:

  • Start date of delay
  • Activities affected
  • Critical path effect
  • Number of delay days
  • Responsible party

D. Cumulative delay impact

At the final window, you identify:

  • Total project delay
  • Attribution of delay by window
  • Contractor/Owner delays
  • Extension-of-Time entitlement


7️⃣ FINAL OUTPUT

You should now have: ✔ A window-by-window delay breakdown ✔ A timeline of critical path shifts ✔ Delay attribution (Contractor vs Owner) ✔ Support for Extension-of-Time claims

To view or add a comment, sign in

Explore content categories